1
|
AUSWSAT67215A
|
(8) IE-4102 A/B STACK SECTION/WHRU SUPPORT STEEL STRUCTURE / SILENCER SUPPORT STEEL STRUCTURE, 2E-4102A/B, (4) TURBINE DOWNSTREAM DUCT,(2) SILENCER TRANSITION DUCT, (2) SILENCER U PSTREAM DUCT, (2) SILENCER DUCT, (4) SILENCERDOWNSTREAM DUCT, (4) WHRU UPSTEAM DUCT, (2) STEEL CASING WHRU INLET LOWER PLENUM DUCT, (2, ) STEEL CASING WHRU INLET UPPER PLENUM DUCT, (2) WHRU TO CO CATALYST TRANSITION DUCT, (2) CO CATALYST SECTION, (2) STACK TRANSITION, (2) SECTION, (2) HANDRAIL INLET DUCT, (2) LADDER WHRU INLET PLENUM, (2) PLATFORM OF STACK, (2) HANDRAIL STACK, (2) LADDER WHRU STACK, (2)ACCESSORY, (4) BOLT/NUTS/WASHERS 647,154.718 490.4, (8) PLATFORM WHRU INLET DUCT, (2) WHRUSUPPORT STEEL STRUCTURE, (6) SILENCER SUPPOR T STEEL STRUCTURE.
|
RGLNG PROJECT
|
N/A
|
2025-05-26
|
Thailand
|
810851 Kgs
|
70 PKG
|